Solar, Battery, and Backup Power: An 8-Step Procurement Checklist for Smaller Facilities

A practical procurement checklist for evaluating solar, battery storage, and backup power at a small-to-mid-size facility — covering load sizing, wind vs solar, grid-scale storage economics, portable power limits, contract traps, and the handover step almost everyone skips.

Who this checklist is for

This is for whoever gets handed “look into solar” on top of a job that is already full. For me that is facilities and vendor purchasing at a 60-person company — roughly $180,000 a year across a dozen suppliers, reported up to both operations and finance. I am not an engineer. I do not design systems. I run the process that gets us to a signed contract we do not regret eighteen months later.

Eight steps, in the order I would actually run them. It works for a 5,000 sq ft office and for a 90,000 sq ft light-industrial building. It also works when a vendor politely implies your project is too small to be worth their scheduling time — more on that in Step 7.

Step 1: Pull twelve months of bills before you talk to anyone

Two numbers matter and most solar proposals only address one of them.

The first is kWh — energy, what you actually consume. The second is kW — demand, the peak you hit on your worst fifteen-minute interval of the month. Solar offsets kWh. It does almost nothing for a demand charge unless you pair it with storage and controls, and demand charges are frequently 30–40% of a commercial bill.

Get all twelve months. Not three. I made that mistake in 2021 on a different category of spend — sampled a mild spring quarter, and my peak number came in about 40% low. That error went into a budget request that finance then had to correct in front of a VP. Not a great week.

Checkpoint before moving on: you should be able to state your annual kWh, your summer peak kW, and whether your rate schedule is demand-based, time-of-use, or both.

Step 2: Separate the solar problem from the backup problem

These get merged in every sales conversation and they are not the same purchase. Solar is a cost-of-energy decision. Backup is an uptime decision. One can be justified on payback, the other on what a four-hour outage costs you in spoiled inventory, lost transactions, or staff sitting in a dark office.

Write down which one you are actually solving for. If the answer is both, budget for both, because a battery sized for arbitrage is usually not sized for outage coverage.

Step 3: Rule out wind early, with numbers

Every wind turbine vs solar panel comparison I have sat through ends the same way, but it is worth doing the math yourself so nobody can wave a catalogue at you.

Small wind needs consistent average wind speed — realistically 10 mph or better at hub height — plus tower height, setbacks, a structural review, permitting that varies block by block, and moving parts that need service. Urban and suburban rooftops rarely clear the first bar. Solar has no moving parts, its output is predictable within a few percent, and the permit path is well-trodden in most jurisdictions.

Short version: unless you have real acreage and a measured annual average wind speed, wind is a distraction. (Should mention: a metered wind study is the only way to know, and it takes a year. Nobody budgets a year for that.)

Step 4: Understand what grid-scale battery storage benefit does and does not do for you

Grid scale battery storage benefit is real — frequency regulation, capacity adequacy, peak shaving at the wholesale level, faster ramping than peakers. What it is not is a line item on your bill.

The benefit reaches you indirectly, through capacity markets, demand-response programs, and whatever your utility has filed with the regulator. Some states have meaningful commercial demand-response programs. Some have almost nothing. Check your state’s public utility commission filings and DSIRE database before you let a vendor fold “grid services revenue” into your payback model.

Here’s something vendors won’t tell you: the savings figure in a proposal is often calculated against a rate schedule you are not actually on. Ask them to name the exact tariff schedule the model assumes, then open your bill and compare the code printed on it.

Step 5: Be honest about what portable power can and cannot do

When someone asks whether an expandable portable power station — something in the class of the Pecron E2000LFP, roughly 2 kWh of LFP capacity with expansion ports — can cover the office, the answer is no, and the useful follow-up is what it can do.

It can run a small IT closet, a couple of workstations, a router and switch stack, temporary lighting, or a jobsite laptop bank. It cannot carry a rooftop HVAC unit or a building-level transfer switch. If you are comparing one to a fixed battery, you are comparing a cooler to a refrigerator.

If you do buy one, check four things: continuous versus surge rating, pure sine wave output, whether the expansion port is a proprietary standard, and UL listing. A 2 kWh unit with a modified sine wave will make a UPS unhappy.

Step 6: Read the financing contract like an adversary

This is where solar deals turn into solar stories. Search for any large provider plus the words “solar lease” and “complaints” — including Sunrun, including everyone else — and you will find a long trail of them. Read a dozen. Most trace back to the same handful of clauses, which means you can check for them in twenty minutes.

The clauses that matter:

  • Escalator. The annual percentage increase on lease or PPA payments. 0.9%, 1.9%, 2.9% — over 25 years the difference is not small. Ask for it in writing as a dollar schedule, not a percentage.
  • Buyout formula. How the early-purchase price is calculated, and whether it is fixed or re-derived each year. A formula you cannot reproduce on a calculator is a formula you cannot plan around.
  • Transfer on sale. What happens to the agreement if you sell the building. If the buyer has to qualify and approve, that is a real constraint on your exit.
  • Roof and structural responsibility. Who pays if the roof needs replacement in year nine, and who pays for removal and reinstallation.
  • Production guarantee. What the provider owes you if the system underperforms, and how underperformance is measured — against a weather-adjusted model or against last year.
  • End-of-term options. Renewal, removal, or purchase, and who pays for removal.

Also skim the FTC’s consumer guidance on solar and your state attorney general’s consumer alerts before signing. Both are free and both are faster than a lawyer’s first hour. Then still use a lawyer for the actual contract — around $1,200 to $2,400 depending on scope, which is cheap next to a 25-year obligation.

Step 7: Vet the vendor on service, not just on price

Price is the easiest thing to compare and the least useful thing to compare. Ask instead:

Who performs service in year eight — the installer, a subcontractor, or a call center? What is the contracted response time for a system-down ticket? Is the workmanship warranty tied to the company, and what happens to it if that company is acquired? Get the monitoring platform in your name, not the installer’s.

National providers like Sunrun have real advantages here: lease and PPA structures that reduce upfront capital, and an integrated battery product (Brightbox) rather than a third-party add-on. What you are buying in exchange is less control over the installation crew. Ask for the crew’s local references and actually call two of them.

And on the small-project question: a 40 kW system is a rounding error to a national installer and a meaningful job to a regional one. Neither is wrong. But a vendor who treats your $18,000 job as an inconvenience will treat your service ticket the same way. When I was starting out, the vendors who took my $200 orders seriously are the ones I still call for $20,000 orders. Small doesn’t mean unimportant — it means unproven, and unproven is fixable.

Step 8: Build the handover document — the step almost everyone skips

This is the one I would put money on you skipping. After commissioning, you should hold:

  • As-built drawings and the single-line diagram, in your own files
  • Admin-level access to the monitoring portal under a company email, not an installer account
  • Warranty registration confirmations for panels, inverter, and battery — separately, since they expire separately
  • The emergency shutdown procedure, printed, in the electrical room
  • One page listing every serial number

I skipped this on a generator install in 2022 and spent three weeks chasing serial numbers through a subcontractor who had changed hands. Cost me nothing in dollars and a fair amount in credibility.

Common mistakes to avoid

Sizing on kWh only. If you never looked at your demand charge, your savings model is probably wrong.

Signing before the interconnection is approved. Utility timelines vary widely and net metering rules have changed in several states. Confirm the current rule and the queue position in writing.

Letting the installer hold the monitoring account. When they lose interest in you, so does your data.

Treating a portable power station as backup infrastructure. It is a stopgap for small loads. Plan it as one.

Comparing quotes on gross price. Compare on total cost of ownership: escalator, buyout, removal cost at end of term, and expected service calls.

Assuming the first proposal is the final one. It almost never is. There is usually room to move on the escalator, the term, or the escalation start date once you have demonstrated you are a serious buyer rather than a shopping exercise.


Written by Isabel Moreno